Dey Gas Field's 58-Kilometer Pipeline Due This Winter, Lifting Capacity by 1.4 Million Cubic Meters to 4 Million a Day

Sahmino Newsroom | 19 November 2026 | yesterday

The chief executive of the Iran Central Oil Fields Company said the 58-kilometer gas transmission pipeline of the Dey field will be completed this winter. According to him, once the line is in service the field's gas production and transmission capacity rises by 1.4 million cubic meters a day to 4 million cubic meters, which implies a current capacity of about 2.6 million cubic meters a day (Sahmino's calculation). Shana reported on Thursday, 19 November 2026 (28 Aban 1405) that Peyman Imani, on a visit to the field's 12-inch pipeline on Wednesday, 18 November 2026 (27 Aban), rated the project's progress favorable.

So far 25 kilometers of the 58-kilometer route, which crosses difficult terrain, have been built, and work continues toward the Dalan refinery. Imani said the cash the project needs has been secured and pipe is being delivered to the site as work advances. He said drilling of two new wells is under way and that, once they come on stream, the field's output will reach its maximum allowed sustainable rate of 5 million cubic meters a day. The power supply project for the wells and the field's gathering center has also been completed.

The Dey field lies in Farashband county, Fars province, and its gas is sweet, so unlike many of the country's gas fields it does not need extensive processing or sweetening.

Reference:ShanaThe original report

Sahmino context

What the prices have done since this story was published, and what Sahmino wrote around it

Over the same days, Brent Crude rose 0.1 percent, to 92.39 dollars.

Over the same days, Gold ounce fell 4.1 percent, to 3,517 dollars.

Brent Crude
+0.1%
Gold ounce
−4.1%

Prices to the close of 20 November

More from this market