Pars Oil and Gas Reports Handover of Newly Completed Equipment at South Pars Phase 13
19 October 2026 | 2 days ago
Pars Oil and Gas Company said on Monday 19 October 2026 (27 Mehr 1405) that some newly completed equipment and units at the South Pars Phase 13 refinery had been commissioned and handed over to their final operator, the South Pars Gas Complex. The company's deputy for development projects listed the gas-dehydration and ethane-recovery compressors, carbon dioxide equipment for the fire-suppression system, the southern butane tank and the refinery's gasoline pump unit among the handed-over facilities.

File image of the South Pars Gas Complex Phase 8 refinery
Source: Mehr News

Mehr archive image accompanying its report on the South Pars Phase 13 refinery
Archive photo | Source: Mehr News
The onshore project manager also reported completion and commissioning of the sulphur-recovery unit, while the tail-gas treatment section remains in the commissioning process. A condensate-stabilisation compressor is planned for commissioning next month, and the company says it is working to complete the remaining onshore facilities by the end of Azar 1405; both are plans, not completed works.
More from this market
Qatari Official Urges Continued Talks With Tehran and Rejects Strait of Hormuz Transit Fees
Al Jazeera | 2 days ago
Brent Slips About 1.6% Toward $108 on Monday After Last Week's 5% Rally
Economic data service | 2 days ago
Reuters: Global Food Inflation Could Last Into 2027; FAO Index Stood at 136 Points in September
Mehr News Agency, citing Reuters | 2 days agoFeed Grain Clearance at Northern Ports Hinges on Unsettled Eurasian Union Quota
Mehr News Agency | 2 days ago