Central Oil Fields Company Reports First-Half 1405 Output Above Plan: South Zagros Gas at 106 Percent, Western Oil at 103 Percent
12 October 2026 | 8 days ago
In a report carried by Mehr on Monday, 12 October 2026 (20 Mehr 1405), Iran's Central Oil Fields Company said output in the first six months of 1405 exceeded approved plans in several areas. In South Zagros, gas production reached 106 percent of plan and oil 101 percent; in the west of the country, oil output was 103 percent of plan and gas at the Tang-e Bijar field 106 percent. Gas production in the east of the country was 1 billion cubic metres higher than in the same period a year earlier.
According to figures from the South Zagros oil and gas operating company, the area produced about 24,945 million cubic metres of gas, 6.7 million barrels of gas condensate and about 1.4 million barrels of crude oil over the same period. The Parsian fields supply about 41 percent of South Zagros gas.
For the four winter months, daily South Zagros output is forecast at about 161 million cubic metres of gas, against an official obligation of 159.6 million cubic metres for the period. The figures are the company's own and have not been confirmed by an independent source.
More from this market
Kremlin Rejects Zelenskyy's 60-Day Truce as Kyiv Reports Violations of the "Energy Ceasefire" and the EU Adds 1,600 Sanctions
Al Jazeera | 8 days agoSupreme Mining Council Rules That First-Half 1405 Mining Royalties Be Charged on Actual Extraction
Mehr News Agency, citing the Iran Chamber of Commerce | 8 days agoOil Ministry Approves Outsourcing Aircraft Refuelling Centres in Three Clusters
EcoIran, citing the National Oil Refining and Distribution Company | 8 days agoTehran Calls the Arab Oil Shuttle Route Out of the Southern Strait of Hormuz an "Explicit Target"; Windward Reports Surging Ship Attacks
Al Jazeera | 8 days ago